| PROGRAMME | Environment and Climate Action Sector Operational Programme |
| PRIORITY AREA | Water (Infrastructure Activities) |
| BENEFICIARY(IES) | Rize Municipality |
| PLACE | Rize |
| ABOUT THE PROJECT | Overall Objective of the project is:
To contribute to the improvement of public health by addressing the gap in legislative compliance, and to enhance the water quality of the Black Sea, thereby supporting Türkiye’s environmental protection efforts and alignment with the EU wastewater sector directives within the accession process Specific Objectives of the Project:
|
| COMPONENTS AND BUDGETS OF THE PROJECT | |
|
CONTRACT 1 |
|
| NAME OF THE CONTRACT | Rize Integrated Water Project Technical Assistance and Consultancy Works |
| BUDGET OF THE CONTRACT | 1,499,525.00 Euros |
| START DATE | 01/02/2021 |
| END DATE | Ongoing. |
|
CONTRACT 2 |
|
| NAME OF THE CONTRACT | Rize Wastewater Treatment Plant Construction Works Contract |
| BUDGET OF THE CONTRACT | 13,856,641.05 Euros |
| START DATE | 30/04/2021 |
| END DATE | Ongoing |
| PHYSICAL PROGRESS | 50% |
|
CONTRACT 3 |
|
| NAME OF THE CONTRACT | Rize Wastewater Collector System Construction Works Contract |
| BUDGET OF THE CONTRACT | 4,553,000.00 Euros |
| START DATE | 03/2021 |
| END DATE | Terminated. |
| PHYSICAL PROGRESS | 34% |
LOCATION: