| NAME OF THE PROGRAMME | Environment Operational Programme (2007–2013) |
| START DATE | 28/12/2015 |
| END DATE | 15/11/2019 |
| BENEFICIARY(IES) | Şanlıurfa Metropolitan Municipality |
| PLACE | Şanlıurfa |
| BUDGET OF THE CONTRACT | 29,695,813.79 Euros |
| ABOUT THE PROJECT | A wastewater treatment plant with an average flow of 145,000 m³/day and a capacity equivalent to 721,000 population, designed to serve 636,000 people until the year 2030, has been constructed within the scope of the project.
It includes the renewal of the existing Kara Köprü wastewater main collector and the construction of an additional line (12 km), the construction of the Yenice – Agricultural City collector (2.6 km) and the construction of the foothill collector (7 km). |
| CONTRACTS WITHIN THE SCOPE OF THE PROJECT | |
| Technical Assistance and Consultancy Service Contract | |
| Şanlıurfa Wastewater Treatment Plant Construction | |
| Şanlıurfa Wastewater Collector Lines Renewal Works | |
| Supply (Procurement) Contract Lot-1 | |
| Supply (Procurement) Contract Lot-2 | |