| NAME OF THE PROGRAMME | Environment Operational Programme (2007–2013) |
| START DATE | 02/05/2013 |
| END DATE | 15/12/2017 |
| BENEFICIARY(IES) | General Directorate of Gaziantep Metropolitan Municipality Water and Sewerage Administration (GASKİ) |
| PLACE | Gaziantep/Nizip |
| BUDGET OF THE CONTRACT | 12,594,747.73 Euros |
| ABOUT THE PROJECT | Within the scope of the project, the consultancy of the construction contract has been carried out; the technical capacity of Gaziantep Metropolitan Municipality and GASKİ has been strengthened; the implementation projects of the Wastewater Treatment Plant and Collector Lines have been prepared; and the documentation for the procurement of supplies has been prepared.
In addition, a 7,500 m³ drinking water reservoir (DY4), a 1,000 m³ drinking water reservoir (DY5), a pumping station, 228 km of drinking water transmission line and drinking water distribution network construction, as well as approximately 12,327 drinking water subscriber connections, have been completed. |
| CONTRACTS WITHIN THE SCOPE OF THE PROJECT | |
| Technical Assistance and Consultancy Service Contract | |
| Nizip Drinking Water Supply Construction Works | |
IPA I/Projects/Water Management Projects
Nizip Water and Wastewater Project