| NAME OF THE PROGRAMME | Environment Operational Programme (2007–2013) |
| START DATE | 27/11/2015 |
| END DATE | 22/12/2018 |
| BENEFICIARY(IES) | Merzifon Municipality |
| PLACE | Amasya/Merzifon |
| BUDGET OF THE CONTRACT | 6,177,084.94 Euros |
| ABOUT THE PROJECT | Within the scope of the project, the administrative, technical and financial capacity of the Project Implementation Unit/Water and Sewerage Administration has been strengthened; the construction of the Merzifon wastewater treatment plant with a capacity of 8,952 m³/day has been carried out; the supervision of the rehabilitation works of the existing drinking water supply and distribution lines has been undertaken; and the necessary documentation for equipment procurement has been prepared, together with the provision of technical assistance during the post-tender processes.
Within the scope of the construction contract, the first stage of the wastewater treatment plant construction has been completed. |
| CONTRACTS WITHIN THE SCOPE OF THE PROJECT | |
| Technical Assistance and Consultancy Contract | |
| Merzifon Wastewater Treatment Plant Construction | |
| Supply (Procurement) Contract Lot-1 | |
| Supply (Procurement) Contract Lot-2 | |
| Supply (Procurement) Contract Lot-3 | |
| Supply (Procurement) Contract Lot-4 | |
IPA I/Projects/Water Management Projects
Merzifon Wastewater Project