| NAME OF THE PROGRAMME | Environment Operational Programme (2007–2013) |
| START DATE | 02/08/2012 |
| END DATE | 15/08/2017 |
| BENEFICIARY(IES) | Adana Metropolitan Municipality |
| PLACE | Adana/Ceyhan |
| BUDGET OF THE CONTRACT | 18,588,015.50 Euros |
| ABOUT THE PROJECT | Within the scope of the Project, a wastewater treatment plant with an average flow of 34,900 m³/day and a service capacity of 100,000 persons was designed and constructed by the Contractor, and training on operation and maintenance was provided to the staff of the Adana Water and Sewerage Administration.
By rehabilitating the existing plant that carried out physical treatment, it was transformed into a facility capable of secondary biological treatment, removing carbon and nitrogen. By using the biogas generated in anaerobic sludge digesters, a certain portion of the facility’s energy demand is met. In addition, the construction of a 26.5 km stormwater, siphon and discharge structures was carried out to serve 30% of the district. |
| CONTRACTS WITHIN THE SCOPE OF THE PROJECT | |
| Technical Assistance and Consultancy Service Contract | |
| Ceyhan Wastewater Treatment Plant Construction | |
| Ceyhan Stormwater Drainage Network Construction Project | |
| Supply (Procurement) Contract Lot-1 | |
| Supply (Procurement) Contract Lot-2 | |
| Supply (Procurement) Contract Lot-3 | |
IPA I/Projects/Water Management Projects
Ceyhan Wastewater and Stormwater Project