| PROGRAMME | Environment and Climate Action Sector Operational Programme |
| PRIORITY AREA | Water (Infrastructure Activities) |
| BENEFICIARY(IES) | Çankırı Municipality |
| PLACE | Çankırı |
| ABOUT THE PROJECT | Overall Objective of the project is:
To support the accession process by strengthening the infrastructure and water management of Çankırı, and by ensuring Türkiye’s compliance with environmental protection and EU wastewater sector directives Specific Objectives of the Project:
|
| PROJECT WEBSITE | https://x.com/cankiriatiksu |
| COMPONENTS AND BUDGETS OF THE PROJECT | |
| CONTRACT 1 | |
| NAME OF THE CONTRACT | Çankırı Wastewater Project Technical Assistance and Consultancy Contract |
| BUDGET OF THE CONTRACT | 1,282,950 Euros
|
| START DATE | 20/09/2021 |
| END DATE | Ongoing |
| CONTRACT 2 | |
| NAME OF THE CONTRACT | Çankırı Wastewater Treatment Plant Construction Works Contract (Lot 1) |
| BUDGET OF THE CONTRACT | 12,586,762.04 Euros
|
| START DATE | 28/02/2022 |
| END DATE | Ongoing |
| PHYSICAL PROGRESS | 80% |
| CONTRACT 3 | |
| NAME OF THE CONTRACT | Çankırı Wastewater Collector Project Construction Works Contract (Lot 2) |
| BUDGET OF THE CONTRACT | 4,716,970.13 Euros |
| START DATE | 01/12/2021 |
| END DATE | Ongoing |
| PHYSICAL PROGRESS | 75% |
LOCATION: