IPA I/Projects/Water Management Projects

Nizip Water and Wastewater Project

NAME OF THE PROGRAMME Environment Operational Programme (2007–2013)
START DATE 02/05/2013
END DATE 15/12/2017
BENEFICIARY(IES) General Directorate of Gaziantep Metropolitan Municipality Water and Sewerage Administration (GASKİ)
PLACE Gaziantep/Nizip
BUDGET OF THE CONTRACT 12,594,747.73 Euros
ABOUT THE PROJECT Within the scope of the project, the consultancy of the construction contract has been carried out; the technical capacity of Gaziantep Metropolitan Municipality and GASKİ has been strengthened; the implementation projects of the Wastewater Treatment Plant and Collector Lines have been prepared; and the documentation for the procurement of supplies has been prepared.

In addition, a 7,500 m³ drinking water reservoir (DY4), a 1,000 m³ drinking water reservoir (DY5), a pumping station, 228 km of drinking water transmission line and drinking water distribution network construction, as well as approximately 12,327 drinking water subscriber connections, have been completed.

CONTRACTS WITHIN THE SCOPE OF THE PROJECT
  Technical Assistance and Consultancy Service Contract
  Nizip Drinking Water Supply Construction Works