| NAME OF THE PROGRAMME | Environment Operational Programme (2007–2013) |
| START DATE | 20/12/2011 |
| END DATE | 12/12/2017 |
| BENEFICIARY(IES) | Doğubayazıt Municipality |
| PLACE | Ağrı/Doğubayazıt |
| BUDGET OF THE CONTRACT | 28,748,218.66 Euros |
| ABOUT THE PROJECT | Through the Project, it was aimed to provide the district centre with 24-hour uninterrupted safe drinking water supplied from Balık Lake, to collect the generated wastewater and convey it to the wastewater treatment plant planned to be constructed under IPA II funds by means of wastewater collectors, thereby contributing to the creation of a healthier environment in the region.
Within the scope of the project;
was carried out. |
| CONTRACTS WITHIN THE SCOPE OF THE PROJECT | |
| Technical Assistance and Consultancy Contract | |
| Drinking Water Supply Construction Works Contract | |
| Wastewater Collectors and Network Construction | |
IPA I/Projects/Water Management Projects
Doğubayazıt Drinking Water Supply Project