IPA I/Projects/Water Management Projects

Soma Wastewater Project

NAME OF THE PROGRAMME Environment Operational Programme (2007–2013)
START DATE 26/10/2015
END DATE 09/12/2018
BENEFICIARY(IES) Manisa Metropolitan Municipality
PLACE Manisa/Soma
BUDGET OF THE CONTRACT 6,330,417.36 Euros
ABOUT THE PROJECT Within the scope of the project, the first stage construction of the Soma wastewater treatment plant with a capacity of 13,764 m³/day, and the completion of the main collector line of 850 m in length with a diameter of 1,200 mm, have been carried out. The wastewater collector of Turgutalp Town has been connected to the main wastewater collector by means of a 50 m long concrete pipe with a diameter of 300 mm. The treated water collector has been connected to the Bakırçay Stream by means of a 152 m long concrete pipe with a diameter of 1,000 mm.
CONTRACTS WITHIN THE SCOPE OF THE PROJECT
  Technical Assistance and Consultancy Service Contract
  Soma Wastewater Treatment Plant Construction
  Equipment Supply Contract (Lot-1)
  Equipment Supply Contract (Lot-2)