IPA I/Projects/Water Management Projects

Seydişehir Wastewater Project

NAME OF THE PROGRAMME Environment Operational Programme (2007–2013)
START DATE 05/01/2015
END DATE 09/03/2020
BENEFICIARY(IES) Konya Metropolitan Municipality

General Directorate of KOSKİ

PLACE Konya/Seydişehir
BUDGET OF THE CONTRACT 5,294,468.68 Euros
ABOUT THE PROJECT Within the scope of the project, the administrative, technical and financial capacity of the Project Implementation Unit/Water and Sewerage Administration has been strengthened, the tender documents for the restructuring of water distribution have been prepared, and the construction works have been supervised.

Within the scope of the project, a wastewater treatment plant with an annual capacity of 2.2 million m³, designed to serve 46,000 people by the target year 2025, together with its associated structures, has been constructed, and approximately 8 km of collector line has been extended.

CONTRACTS WITHIN THE SCOPE OF THE PROJECT
  Technical Assistance and Consultancy Service Contract
  Seydişehir Wastewater Treatment Plant Construction
  Seydişehir Wastewater Treatment Plant Construction (Completion of Remaining Works)
  Supply (Procurement) Contract Lot-4