IPA I/Projects/Water Management Projects

Akşehir Wastewater Project

NAME OF THE PROGRAMME Environment Operational Programme (2007–2013)
START DATE 29/12/2015
END DATE 01/04/2019
BENEFICIARY(IES) Konya Metropolitan Municipality
PLACE Konya/ Akşehir
BUDGET OF THE CONTRACT 12,458,840.90 Euros
ABOUT THE PROJECT Within the scope of the Contract, the activities carried out included the supervision of the first component, namely the Akşehir Wastewater Treatment Plant and Wastewater Collectors Construction Works; the strengthening of KOSKİ’s technical capacity; and the preparation of tender documents for Equipment Supply.

The Project consists of two parts: the first part is the construction of one wastewater treatment plant with a capacity of 15,102 m³/day (first stage – 2025); the second part is the construction of approximately 33 km of wastewater collectors. The wastewater treatment plant has the capacity to serve an equivalent population of 63,000. The final acceptance of the plant was carried out on 09 December 2018

CONTRACTS WITHIN THE SCOPE OF THE PROJECT
  Technical Assistance and Consultancy Service Contract
  Akşehir Wastewater Treatment Plant and Wastewater Collectors Construction Works
  Supply (Procurement) Contract Lot-1
  Supply (Procurement) Contract Lot-3
  Supply (Procurement) Contract Lot-4