| PROGRAMME | Environment and Climate Action Sector Operational Programme |
| PRIORITY AREA | Water (Infrastructure Activities) |
| BENEFICIARY(IES) | Niksar Municipality |
| PLACE | Tokat, Niksar |
| ABOUT THE PROJECT | Overall Objective of the project is:
To contribute to the improvement of public health by addressing the gap in legislative compliance, and to enhance the water quality of the Black Sea, thereby supporting Türkiye’s environmental protection efforts and alignment with the EU wastewater sector directives within the accession process Specific Objectives of the Project:
|
| COMPONENTS AND BUDGETS OF THE PROJECT | |
|
CONTRACT 1 |
|
| NAME OF THE CONTRACT | Niksar Water and Wastewater Project Technical Assistance and Consultancy Contract |
| BUDGET OF THE CONTRACT | 1,735,850.00 Euros |
| START DATE | 20/04/2020 |
| END DATE | Ongoing. |
|
CONTRACT 2 |
|
| NAME OF THE CONTRACT | Niksar Wastewater Treatment Plant Construction Works Contract (Lot-1) |
| BUDGET OF THE CONTRACT | 6,605,258.99 Euros |
| START DATE | 01/04/2021 |
| END DATE | 31/12/2023 Provisional Acceptance Date |
| PHYSICAL PROGRESS | 100% |
|
CONTRACT 3 |
|
| NAME OF THE CONTRACT | Niksar Water Supply System and Wastewater Collection System Construction Works Contract (Lot-2) |
| BUDGET OF THE CONTRACT | 11,118,135.00 Euros |
| START DATE | 15/05/2020 |
| END DATE | 30/06/2023 Final Acceptance Date |
| PHYSICAL PROGRESS | 100% |
LOCATION: